Right Claim, Wrong Order

25 November 2026 ,  Antony Arvan 151

1.  An arbitrator is not a court. In Radon Projects (Pty) Ltd v N V Properties (Pty) Ltd and Another [2026] ZASCA 155 (18 November 2026) the Supreme Court of Appeal held that an arbitrator’s powers derive from the arbitration agreement and the reference to arbitration, and from nothing else. Where a building contract regulates how and when the contractor is paid, the arbitrator cannot simply award the contractor a sum of money. He must work within the contract’s payment mechanism.

2. The dispute arose in terms of a JBCC Principal Building Agreement (4th Edition, March 2004). The contractor, Radon, claimed an extension of the date for practical completion and, if the extension were granted, a determination of the financial entitlements that flowed from it, such as escalated preliminary costs, an adjustment of the contract price and the reversal of penalties already deducted. The arbitrator extended the date and ordered the employer to pay the resulting amounts. The High Court set the award aside on review. The Supreme Court of Appeal agreed that the arbitrator had exceeded his powers, although on different grounds.

How the contract pays the contractor

3. In terms of the JBCC agreement the principal agent issues an interim payment certificate each month until the final payment certificate is issued, and the employer must pay the amount certified within seven days. The Court treated a payment certificate as a condition precedent to payment. Adjustments are made in later interim certificates or in the final payment certificate and recovery statement. The reference to arbitration does not relieve the parties of their obligations, which include the obligation of the principal agent to issue further payment certificates.

The arbitrator cannot step into the shoes of the principal agent

4. This is the heart of the judgment. Radon relied on the English decision in Prestige & Co Ltd v Brettell, where it was held that an arbitrator may supply a deficiency in the architect’s performance by doing himself what the architect ought to have done. The Court declined to adopt that principle as one of general application. Whether an award sounding in money may be made depends on whether it falls within the arbitrator’s jurisdiction and the terms of the reference, and the Court pointed out that the dictum in Prestige was “by no means unqualified”.

5. The practical result is that the arbitrator (and, by analogy, an adjudicator) does not replace the principal agent and does not issue the certificate or the order for the payment himself. The Court said that, in exercising his jurisdiction, the arbitrator “could do no more than the PA would have done” had the principal agent granted the extension of time. The exceptions recognised in the English cases, such as fraud or collusion between the employer and the architect, were not alleged, and no one suggested that the principal agent had failed to do what he was required to do.

What the arbitrator can do: determine, and direct how it is certified

6. The Court did not leave the contractor without a remedy. The arbitrator may determine the entitlement, here the extension of time and the quantum of what accrued to the contractor as a result. He may then direct the principal agent or the employer to ensure that those determined amounts are brought to account in the next interim payment certificate, or in the final payment certificate and recovery statement. In the Court’s words, the contract requires this. The arbitrator therefore decides what must go into the certificate and how the certificate is to be framed, but the payment itself follows from the certificate and not from the award.

7. It was argued that an award which directs the certification process, and does not order payment, would not be a final award because it leaves the finalisation of the claim to something outside the arbitration. The Court rejected the argument. Because the arbitrator has himself determined the amount, the resolution of that amount is not left to anyone else. The Court held that an entitlement to be compensated for adjustments arising from the way in which the contract was executed “did not translate into a right to payment except in accordance with the contract’s payment provisions”.

8. The employer’s case illustrates the risk of an award for a bare sum. It contended that it had already reversed the penalties in later interim certificates, but it was not permitted to adduce evidence of certificates issued after the reference. An order to pay a fixed sum would have taken no account of that, and the Court observed that the later certificates highlighted the limits of the arbitrator’s power to make the award that he did. The arbitrator, it held, “misconceived the task he was required to perform” and granted payment orders outside the ambit of his jurisdiction.

Jurisdiction must be decided, not assumed

9. The Court also stressed that an arbitrator does not have the exclusive right to decide the scope of his own jurisdiction, because an award made in excess of his powers is reviewable in terms of section 33(1) of the Arbitration Act 42 of 1965. A preliminary, prima facie view that he has jurisdiction is therefore no safe foundation for the award.

Framing the claim

10. An award that is set aside after years of proceedings is an expensive outcome for a contractor with a sound claim, and the dispute in Radon has been running for many years without a final payment certificate.

11. We recommend that a claim in arbitration or adjudication in terms of a certificate-based contract be framed as follows:
(a) seek a determination of the entitlement, such as the extension of time and the resulting quantum;
(b) seek a direction that the amount be included in the next interim or the final payment certificate, in the form the contract requires;
(c) avoid a prayer for a bare money judgment unless the contract clearly allows it; and
(d) record the basis of the tribunal’s jurisdiction in the referral and obtain a final ruling if it is challenged.

12. The judgment concerned arbitration. The same reasoning should apply by analogy to an adjudicator, whose authority is likewise derived from the contract and the referral, and the prudent course in adjudication is to frame the relief in the same way.

This article is a general commentary and is not legal advice. Please contact us before acting on any aspect of it.

Should you have any queries, please do not hesitate to contact:

Antony Arvan

Director 

BA LLB (UCT) | Arbitrator | Association of Arbitrators (Southern Africa)

antony@mpw.co.za | 021 419 7115 | 083 300 4364

 

Disclaimer: This article is the personal opinion/view of the author(s) and does not necessarily present the views of the firm. The content is provided for information only and should not be seen as an exact or complete exposition of the law. Accordingly, no reliance should be placed on the content for any reason whatsoever, and no action should be taken on the basis thereof unless its application and accuracy have been confirmed by a legal advisor. The firm and author(s) cannot be held liable for any prejudice or damage resulting from action taken based on this content without further written confirmation by the author(s).